First production from Hummer development late due to bad weather

Hummer Main Pass Block 270 "B" production platform

First production from the Castex Energy-operated Hummer field development in the U.S. Gulf of Mexico has been delayed due to recent harsh weather conditions in the region.

Petsec Energy, an independent oil and gas exploration and production company and Castex’s partner in the project, said on Tuesday that the previous guidance for first production from Hummer was set for late third quarter 2017/early October 2017.

As a result of recent weather events in the Gulf of Mexico, namely Hurricane Harvey and Hurricane Irma, the completion of the modifications to the four pile deck have been delayed. Another consequence of extreme weather in the Gulf were related equipment delays.

The estimated date to complete construction and load out of a four pile deck, currently being modified to accommodate the extent of the designed facilities and future expansion, is now mid-October. This, according to Petsec, will move first production guidance for the Hummer project to mid or late November.

To remind, the Hummer oil and gas field extends over Main Pass Blocks 270,273, and 274 offshore Louisiana, USA.

The Hummer project discovery well, Main Pass 270 #3 BP 1, is located in U.S. federal waters some 50 miles southeast of Venice, Louisiana. The water depth at the location is approximately 215 feet. The well was drilled, logged and temporarily suspended during mid-late 2015.

A platform jacket was installed over the well, and the well was completed and tested in late 2016. Test rates recorded over the last three hours of the test period averaged 19.88 MMcfpd and 396 bopd on a 16/64-inch choke with a flowing well head pressure of 9,753 psi. The rates continued to increase over the final flow period.

Following the production test, the well was suspended pending installation of the deck, production facilities, and pipelines.

In January 2017, a turnkey contract was awarded for the design, engineering, modification, and fabrication of production facilities, and installation of the platform deck onto the already installed jacket for the Hummer Main Pass Block 270 “B” production platform and for the planning, installation and hook-up of the pipelines connecting the platform to gas and oil sales pipelines.

Share this article

Follow Offshore Energy Today

Events>

<< Nov 2017 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

OTC Asia 2018

The biennial OTC Asia is where energy professionals meet to exchange ideas and opinions to advance scientific and technical knowledge…

read more >

THE 5TH OIL & GAS VIETNAM 2017

The 5th edition of Oil & Gas Vietnam (OGAV) exhibition 2017 is the only specialized event in Vietnam that brings together an international…

read more >

FPSO Europe Congress 2018

The FPSO Europe Congress 2018 builds on these themes, lending a particular focus to FPSO Value Preservation and Operational Excellence…

read more >

Arabia 2018 Conference and Exhibition

Offshore Arabia is a focused prestigious meeting place of the Offshore Industry, and it’s diverse spectrum from the Oil & Gas…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you’ll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you’ll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you’ll reach countless professionals in the sector. For more information, click below...

apply