Steel Cutting Ceremony Held for Cygnus Alpha Wellhead Platform (UK)

Steel Cutting Ceremony Held for Cygnus Alpha Wellhead Platform (UK)

The ceremonial first cut of steel for the £1.4 billion (GBP) Cygnus gas field project was celebrated today by operator GDF SUEZ E&P UK and partners Centrica Energy and Bayerngas at Heerema Fabrication Group’s Hartlepool yard in North East England.

Stuart Drummond, mayor of Hartlepool, performed the first cut of the steel, which will be used to build the 1,600 tonne Cygnus Alpha Wellhead Platform, the first of four platforms for the Cygnus field – the largest gas discovery in the Southern North Sea in the last 25 years.

After project sanction in August 2012, GDF SUEZ E&P UK placed a frame contract with Heerema Fabrication Group’s Hartlepool yard with the intent to place future call-off orders for the fabrication and commissioning of three of the four topsides and a compression module for the Cygnus development. The project is expected to create more than 1 million man hours of fabrication and around 450 people working on Heerema’s Hartlepool site for the project during 2014.

Approximately £1.4 billion (GBP) is being invested in the Cygnus project, with the intent to maximise UK-based company content, creating 4,000 direct and indirect jobs during the construction phase.

Stuart Drummond, Mayor of Hartlepool, said: “I’m delighted that Heerema have once again secured a major international frame contract that will both safeguard and create hundreds of jobs in Hartlepool. It shows that, despite the global financial crisis, Hartlepool is well and truly open for business and there is great confidence in the town and our ability to deliver.”

Jean-Claude Perdigues, Managing Director, GDF SUEZ E&P UK said: “Today’s ceremony marks a major milestone in the flagship Cygnus project which is bringing substantial jobs and investment to the UK and notably to the Hartlepool area. Construction work has started swiftly and it is a privilege to witness the cutting of first steel for the Cygnus development, which is making such a positive contribution to the UK energy industry and wider economy.”

Greg McKenna, Southern North Sea Director, Centrica Energy Upstream, said: “The Cygnus project will boost jobs in the Hartlepool area and across the UK, and help to secure long term energy supplies for the future. We look forward to working with our partners and the team in Hartlepool to deliver this project safely.”

Bayerngas UK Ltd, Managing Director, Gerry Harrison commented: “Development planning always spans an extensive period and it’s refreshing to see the start of construction. We look forward to working with our partners and contractors to ensure a safe project, delivered on time and on budget.”

Wim Matthijssen, Chief Operating Officer of Heerema Fabrication Group said: “The first cut steel ceremony is an important milestone in the fabrication process of Cygnus, where we physically commence building the first of the topsides at our Hartlepool yard. Heerema has a reputation and proven track record on delivering high quality projects on time, and most importantly safely. ”

The Cygnus Partnership is led by operator GDF SUEZ E&P UK Ltd (38.75%) with partners Centrica (48.75%) and Bayerngas (12.5%).

Press Release, December 5, 2012

Share this article

Follow Offshore Energy Today

Events>

<< Aug 2015 >>
MTWTFSS
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31 1 2 3 4 5 6

Gas México Congress & Exhibition

The Congress will feature international speakers, the one day Business Program with two days of Technical Presentations, will focus on both…

read more >

Oil and Gas Training

EI Oil and Gas Training offers a comprehensive programme of courses for the oil and gas industry, both as classroom training ranging…

read more >

China International Offshore Oil & Gas Exhibition

China International Offshore Oil & Gas Exhibition (CIOOE) acts as a regular gathering in global petroleum and petrochemical industry…

read more >

Tanzania Oil & Gas Expo 2015

This event will be the hub for key players in the Oil and Gas industry, attracting leading oil, gas and petroleum companies from around the world…

read more >

Jobs>

Electrician

For one of our clients we are looking for a Ships Electrician. Our client is a company with worldwide activities. You will work in a rotation of 4 till 6 weeks on and off.

apply

QC Coordinator Offshore

Do you attach great importance to quality and do you have an affinity with offshore projects? Then read about what Van Oord can offer you.

apply

Assistant Driller

Maersk Drilling Norge AS was established in 1990 and employs a staff of approximately 1000 people.

apply