Aker BP installs Valhall Flank West topsides

The Valhall Flank West topsides were installed on the Aker BP-operated Valhall field located in the North Sea offshore Norway on Saturday, June 22, 2019. First oil from the project is expected in the fourth quarter 2019.

Source: Aker BP

Aker BP said on Saturday that this was just 14 months after the first steel was cut at Kværner’s yard in Verdal. Both the topsides and the jacket were delivered ahead of schedule and under budget. The platform’s jacket was delivered by Kaverner in April this year.

Aker BP is the operator of the Valhall Flank Vest with Pandion as a partner. The platform is the first to be delivered under the wellhead platform alliance between Aker BP, Aker Solutions, Kværner and ABB.

It sailed from Kværner in Verdal on Sunday, June 16 and arrived at the field with no carry-over-work from the yard. That means a significant reduction in the work scope offshore, Aker BP explained.

“This is probably the most complete platform ever installed in the North Sea. All planned construction work is complete and just seven percent of the commissioning phase remains. I am truly impressed by the job the alliance has done here,” said CEO Karl Johnny Hersvik in Aker BP.

“We see a definite effect from the alliance model in the Valhall Flank West project. Compared with similar projects, we have seen substantial reductions in both cost, engineering hours and construction of the topsides and jacket,” said Hersvik.

 

Installation 

 

Heerema’s Thialf lifting vessel placed the 2000-tonne topsides on the jacket at Thursday evening. The entire operation was complete on Saturday morning.

The critical hook-up work starts almost immediately. Initially, crews will be transported to the platform using vessels. The Maersk Invincible jack-up rig is expected to arrive at the field sometime this week. It will drill six wells as part of the project and will function as a living quarters platform in the hook-up and commissioning phase.

“So far, Valhall Flank West has been a fantastic journey and I am proud to lead this team. All the alliances are delivering and the project is successful because we have a solid team that cooperates really well across companies,” says project manager Michael Joseph Bible.

At the Valhall Field Center, the Modification alliance has carried out extensive modifications over the past year to prepare the center to receive the production from Valhall Flank West. In addition, the Subsea alliance has laid pipelines and umbilical which are ready to be pulled in now that the platform is in place.

“We are now entering a demanding offshore period, and we will continue the good work in this phase of the project. The most important thing for us is that everyone working in the project return home safely,” says Bible.

Source: Aker BP

 

First oil in 4Q 2019

 

Valhall has produced one billion barrels since the field opened in 1982. The ambition is to produce another billion barrels during the next 40 years, Aker BP said.

“Valhall Flank West is an important contribution to ensure that we achieve our ambition. The field can contribute around 60 million barrels of oil equivalents to Valhall’s production. The West Flank has capacity for another six wells, and we are now looking into the possibility of more wells and increased value creation from the field,” said Valhall asset manager Per Mikal Hauge.

Aker BP is investing NOK 5.5 billion in Valhall Flank West. The break-even price for the development is $28.5 per bbl. Around 1500 people have been involved in the project.

“There is high activity on the Valhall field. Last week, we removed QP from the field centre, the first of three old platforms that will be taken away. We are also investing in the future of the field with new wells and plugging of shut down wells. We look forward to starting production from Valhall Flank West in the fourth quarter. What has been installed on the field is of very good quality, and that project has set a new standard for project implementation. Today, I would just like to congratulate everyone who has been involved in the field development so far,” Hauge concluded.


Spotted a typo? Have something more to add to the story? Maybe a nice photo? Contact our editorial team via email.

Offshore Energy Today, established in 2010, is read by over 10,000 industry professionals daily. We had nearly 9 million page views in 2018, with 2.4 million new users. This makes us one of the world’s most attractive online platforms in the space of offshore oil and gas and allows our partners to get maximum exposure for their online campaigns. 

If you’re interested in showcasing your company, product or technology on Offshore Energy Today contact our marketing manager Mirza Duran for advertising options.

Share this article

Follow Offshore Energy Today

Events>

<< Jul 2019 >>
MTWTFSS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31 1 2 3 4

Uganda International Oil and Gas Summit 2019

Uganda International Oil & Gas Summit will once again examine the industry’s developments…

read more >

8th OIL & GAS AFRICA 2019 CONFERENCE

OIL & GAS AFRICA is one of the most prime regional & international Oil and Gas conferences in East Africa…

read more >

Gas Indonesia Summit 2019

Gas Indonesia Summit & Exhibition is returning for the fourth edition in Jakarta…

read more >

Shanghai Int Petrochemical and Offshore Oil & Gas and Chemical Industry Technology and Equipment Exhibition 2019

cippe Shanghai has attracts both…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply