Claxton performs first rigless removal of stuck BHA

Claxton Engineering Services Ltd, an Acteon company, has completed the first rigless removal of a stuck bottom hole assembly (BHA). The work was completed during a slot recovery operation using an innovative approach at Maersk’s Tyra East field in the Danish sector of the North Sea.

Claxton 300te Tension Ring Maersk Slot Recovery

The well was drilled in the 1980s and, during construction, the BHA had become stuck in the conductor pipe and prevented well completion. Claxton used its slot recovery methodology and tooling, specialist cutting equipment and a dive support vessel to solve the issue.

The programme began with the deployment of a specialist casing cutting system to remove a section of the conductor, which left the stuck BHA intact, but exposed. This called for modification of the cutting equipment and the subsea application of a system that is normally used on the surface.

Once the conductor had been cut and removed, Claxton engineers prepared a specialised lifting device using an air hoist on deck deployed through an A-frame, while divers clamped the lifting gear to the BHA. The BHA was too heavy to recover in one piece and had to be cut subsea. This involved using two sizes of diamond wire-cutting machine: the smaller to sever only the exposed BHA, and the larger to cut simultaneously through the remaining conductor stump and the BHA. The cut needed to give a smooth and flush surface on the end of the conductor. Once the cutting machine had sliced through the conductor and the BHA, the top section was recovered.

During planning, the orientation of the remaining BHA relative to the conductor stump was uncertain. Claxton created a unique whipstock with a slot beneath the landing plate that would enable it to capture the exposed part of the BHA securely in any orientation. The top half of the whipstock would rotate on this base and enable the new well to be kicked off in any direction. Claxton’s experience in whipstock design ensured an effective design for the project.

The initial project schedule was 20 days. However, the Claxton-led team completed the operation in less than 16 days, including more than three days waiting-on-weather.

Alex Lucas, senior drilling engineer, Maersk drilling department, said: “This was a very challenging piece of work requiring integrated planning across many departments and companies, not to mention the extensive amount of design, manufacturing and testing of equipment that Claxton designed especially for the job in double-quick time.”

Claxton completed the world’s first rigless platform well abandonment over a decade ago and has subsequently deployed its cutting and recovery tooling on more than 270 successful conductor cutting, recovery and abandonment operations.

 

Press Release, July 07, 2014

 

Share this article

Follow Offshore Energy Today

Events>

<< Sep 2019 >>
MTWTFSS
26 27 28 29 30 31 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 1 2 3 4 5 6

Africa Oil & Power 2019

The Africa Oil & Power conference will bring together an elite class of ministers and senior-level government…

read more >

OWI LATAM 2019

Over the two-day conference, 25+ expert speakers will share exclusive insight on how to develop an integrity, production and P&A strategy…

read more >

Uganda International Oil and Gas Summit 2019

Uganda International Oil & Gas Summit will once again examine the industry’s developments…

read more >

Argentina Oil and Gas Expo 2019

The Argentine Oil and Gas Institute (IAPG) organizes the Argentina Oil & Gas Expo bringing together the most…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply