ExxonMobil’s Hebron under the spotlight again after near miss incident

Oil major ExxonMobil has reported a high potential near miss incident on the Hebron platform located offshore Newfoundland, Canada. 

Hebron platform. Source: Wiki Commons; Author: Shhewitt – under the CC BY-SA 4.0 license

Canada’s offshore regulator, the Canada-Newfoundland and Labrador Offshore Petroleum Board (C-NLOPB), informed on the incident at Exxon’s Hebron platform on Thursday, November 29.

According to the regulator, on November 27, 2018, a cement head approximately one meter in height, was secured in the vertical position in a container basket in preparation for loading. While in the process of installing a lifting cap onto the cement head, the cement head came loose from the securing strap and tipped onto its side inside the container basket.

There were two people in the basket at the time of the incident. Ongoing work was immediately stopped, and the area was secured. Although there were no injuries associated with this incident, it had the potential for a major injury as it could have resulted in a fracture, the regulator said.

The area was immediately cleared of all personnel and secured before resuming operations. The C-NLOPB is continuing to monitor ExxonMobil’s investigation of the incident.

Recent shutdown 

Two weeks ago production from the Hebron platform was shut down due to adverse weather conditions. On November 20 C-NLOPB said that operators offshore Canada, including Exxon and its Hebron platform, were checking their offshore facilities for damage before resuming operations.

As there were no storm impacts on Hebron, Exxon proceeded with its plan to start up the platform by slowly introducing hydrocarbons to the facility, but the company still had to inspect the offshore loading system before offloading petroleum from the facility.

On November 23 the offshore regulator informed that Hebron had resumed production.

Discovered in 1980, the Hebron field is estimated to contain more than 700 million barrels of recoverable resources. The Hebron platform consists of a stand-alone gravity-based structure, which supports an integrated topsides deck that includes living quarters and drilling and production facilities. The platform has a storage capacity of 1.2 million barrels of oil. The production started a year ago, in November 2017.

Offshore Energy Today Staff

Share this article

Follow Offshore Energy Today

Events>

<< Jan 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31 1 2

Africa Oil Week 2020

For over 25 years Africa Oil Week has been the meeting place for Africa’s most senior E&P stakeholders.

read more >

CERAWeek 2020

 Each year, CERA clients gathered for a few days in Houston…

read more >

Offshore Technology Conference (OTC) 2020

The Offshore Technology Conference (OTC) showcases leading-edge technology for offshore drilling, exploration…

read more >

2020 EXPLORATION AND PRODUCTION STANDARDS CONFERENCE ON OILFIELD EQUIPMENT AND MATERIALS

The development of consensus standards is one of API’s oldest and most successful programs.

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply