Gazprom completes pipeline system for TurkStream project

The entire pipeline system for Gazprom’s TurkStream project in the Black Sea has been completed following successful connections between TurkStream offshore section and landfalls.

Lorelay

TurkStream is a project for a gas pipeline stretching across the Black Sea from Russia to Turkey and further to Turkey’s border with neighboring countries.

The final weld that connects the offshore and the nearshore sections of TurkStream was completed, marking the finalization of the entire pipeline system in the Black Sea.

The procedure, known technically as “Above Water Tie-In,” involved retrieving the nearshore pipeline and offshore pipeline from the seabed, lifting them above water and welding them together.

The total weight that had to be lifted for the operation was approximately 409 tons. After a thorough inspection of the weld, the pipe was carefully lowered to the seabed at a depth of 32 meters. This operation was carried out on both lines in Russian waters in January and February this year, and near the Turkish coast in March.

The pipelaying in deep waters was carried out by Pioneering Spirit, the world’s biggest construction vessel, while the shallow-water pipelaying was conducted by Lorelay.

With the completion of the Above Water Tie-In Procedure, a physical connection between the landfall facility near the Russian city of Anapa and the Receiving Terminal near Kiyikoy in Turkish Thrace is realized.

Russkaya Compressor Station, which will provide the necessary pressure for the gas to traverse through the Black Sea, and the Anapa landfall facility of the TurkStream pipeline system are already complete and on stand-by.

With the completion of the Receiving Terminal in Kiyikoy later this year, TurkStream will be ready to start operations. Natural gas flow through TurkStream is planned to start by the end of 2019.

The first line of the gas pipeline is intended for the Turkish consumers, while the second line is designated for the Southern and South-Eastern Europe. Each line will have the throughput capacity of 15.75 billion cubic meters of gas per year. South Stream Transport B.V. has been carrying out project activities with regard to the offshore gas pipeline.

Share this article

Follow Offshore Energy Today

Events>

<< Apr 2019 >>
MTWTFSS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 1 2 3 4 5

GeoConvention 2019

GeoConvention offers some of the best local and international insights to efficient energy exploration…

read more >

16th MOSCOW INTERNATIONAL OIL AND GAS EXHIBITION

The Moscow International Oil & Gas Exhibition display products like oil and gas products, oil and gas services…

read more >

Erbil International Oil & Gas Exhibition 2019

The event will be held at the Erbil International Fair Ground which is one of the largest energy related events in Iraq…

read more >

THE 24 th IRAN INTERNATIONAL OIL , GAS , REFINING & PETROCHEMICAL EXHIBITION

The second largest OPEC producer, Iran sits atop 11 percent of oil and 18 percent of gas…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply