Hebron waiting for ice to pass

Hebron waiting for ice to pass

Exxon’s giant Hebron platform in Canada, christened back in April, has yet to sail away to its offshore location.

During the platform launching ceremony held at Nalcor Energy’s Bull Arm Fabrication site, it was said that the sailaway to the Atlantic waters offshore Canada was “imminent.”

It’s been almost a month since then, but the 750.000 metric tonne unit has yet to be moved and installed at the $14 billion Hebron development, 350 kilometers southeast of the Newfoundland and Labrador’s capital St John’s.

CNLOPB, an offshore safety body has issued an operations authorization to ExxonMobil Canada Properties for the Hebron Platform to be towed to field on May 5.

According to Canadian news sources CBC and VOCM, the reason for the hold-up is the ice drifting south from the Baffin Bay.

CBC has cited an Exxon spokesperson who said the tow could happen “within the next couple of weeks.”

The news website even ran the numbers on costs incurred during the waiting period. CBC has come up with up to $5.4 million per that the operator needs to pay for the anchor handling tug supply vessels.

 

Hebron

Once the platform is at the offshore location – the tow will take about two weeks – it will be used to develop Hebron, West Ben Nevis, and Ben Nevis fields. The Hebron project development costs have been estimated at $14 billion.

Estimated recoverable reserves in Hebron are put at 700 million barrels of recoverable resources, making it the second-largest field in the Jeanne d’Arc Basin after Hibernia.

The Hebron platform consists of a stand-alone gravity-based structure, which supports an integrated topsides deck that includes living quarters, and drilling and production facilities. The water depth at the Hebron field is 93 meters.

The sturdy facility consists of a reinforced concrete structure designed to withstand sea ice, icebergs and meteorological and oceanographic conditions. It will have the capacity to store in excess of 1 million barrels of oil in storage compartments. First oil is expected later in 2017.

Offshore Energy Today Staff

Share this article

Follow Offshore Energy Today

Events>

<< Dec 2019 >>
MTWTFSS
25 26 27 28 29 30 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

Africa Oil Week 2020

For over 25 years Africa Oil Week has been the meeting place for Africa’s most senior E&P stakeholders.

read more >

CERAWeek 2020

 Each year, CERA clients gathered for a few days in Houston…

read more >

Offshore Technology Conference (OTC) 2020

The Offshore Technology Conference (OTC) showcases leading-edge technology for offshore drilling, exploration…

read more >

2020 EXPLORATION AND PRODUCTION STANDARDS CONFERENCE ON OILFIELD EQUIPMENT AND MATERIALS

The development of consensus standards is one of API’s oldest and most successful programs.

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply