Iran: South Pars Pipe Laying Near Completion

Pipe laying operations at the South Pars gas field phases 15 and 16 is near completion, the manager of the SP phases 15 and 16, Abolqasem Noubakhti said.

He went on to say that, pipe laying of the phase 16 with 115 kilometers length have been completed while the work in phase 15 is going on with high speed.

Pipe laying of the South Pars gas field phase 15 is also estimated to be finished in next four days, Noubakhti told.

The two phases construction have progressed by 74 percent on average and it is projected onshore sector of the project including its gas processing plant to come on line in December this year.

Meanwhile drilling operations of the mentioned phases have progressed by 67.8 percent.

At the moment 51 thousand meters out of 92 thousand meters of drilling operations are complete

Source:NIGC, August 30, 2011;

Share this article

Follow Offshore Energy Today

Events>

<< Nov 2019 >>
MTWTFSS
28 29 30 31 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 1

Offshore Energy Exhibition and Conference (OEEC) 2020

Offshore Energy addresses the technical, operational and commercial challenges associated with future sector growth.

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply