McDermott achieves several operational milestones

McDermott International, Inc. has announced an update to certain operational matters, including Malaysia (Siakap) Project, the installation of the extended tension leg platform in Brazil (Papa Terra), Azerbaijan (COP) Project, and Australia (Ichthys) Project.

Through working capital management, the Company maintained its previously reported liquidity and leverage position at the end of March 2014 compared to amounts previously reported at the end of February 2014. Specifically, as of March 31, 2014, the Company had approximately $320 million of total cash, cash equivalents, restricted cash and investments and $307 million of total funded debt, including $250 million of borrowings under the Company’s credit facility and $57 million of separate vessel financing.

The Company recently achieved significant operational milestones on several key projects, including:

– Malaysia (Siakap) Project – Pipe and subsea structure installation has been completed. The customer received first oil in February 2014, and the vessel North Ocean 105 has demobilized from the field. The Company expects mechanical completion in early April 2014. Although this project resulted in financial losses recorded in 2013, it was a major technical achievement of complex pipe-in-pipe and subsea structure installation in over 5,000 feet of water.

– Brazil (Papa Terra) Project – The installation of the extended tension leg platform was completed in March 2014 and the vessel DB 50 has demobilized from the field. This facility is a significant operational achievement because it includes the first dry tree in deepwater Brazil.

– Azerbaijan (COP) Project – The Company has progressed work as expected and continues to expect to complete the limited remaining offshore work by mid-May 2014.

– Australia (Ichthys) Project – The Company remains on schedule for fabrication operations in the Batam, Indonesia fabrication yard and anticipates the commencement of the offshore installation operations in the third quarter of 2014. McDermott’s work has resulted in the customer recognizing us as a leader among the program contractors, and the Company expects the work on the project will be a major subsea achievement for the Company.

The Company continues to make progress with customers on commercial matters and, although the Company can provide no assurance, opportunity remains to improve the financial outcome from each of the above-mentioned projects.

April 1, 2014

Share this article

Follow Offshore Energy Today

Events>

<< Dec 2019 >>
MTWTFSS
25 26 27 28 29 30 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

Africa Oil Week 2020

For over 25 years Africa Oil Week has been the meeting place for Africa’s most senior E&P stakeholders.

read more >

CERAWeek 2020

 Each year, CERA clients gathered for a few days in Houston…

read more >

Offshore Technology Conference (OTC) 2020

The Offshore Technology Conference (OTC) showcases leading-edge technology for offshore drilling, exploration…

read more >

2020 EXPLORATION AND PRODUCTION STANDARDS CONFERENCE ON OILFIELD EQUIPMENT AND MATERIALS

The development of consensus standards is one of API’s oldest and most successful programs.

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply