Modus wraps up Vashishta field work

Modus CT1; Source: Modus

Subsea engineering specialist Modus Seabed Intervention has completed work on the ONGC Vashishta pipelines and umbilical offshore India for McDermott International.

Modus said on Thursday that the scope included the trenching and surveying of two 18-kilometer long pipelines with outside diameters of up to 579 millimeters.

The company also did work on a 24-kilometer long 284-millimeter outside diameter umbilical, down to a maximum trench depth of two meters.

The water depth for trenching operations ranged between 3.5 meters and 217 meters and involved mobilizing the Modus CT-1 trenching vehicle onto the Bourbon 807 for the deeper water sections and then transferring the trenching equipment to the Multicat Zwerver II for the shallow water operations. The CT-1 is configured to trench in water depths from 3.5 meters to 3,000 meters.

Nigel Ward, commercial director of Modus Seabed Intervention, said: “We are very pleased to have completed the trenching on this project to specification. The adaptability of CT-1 came into its own; the vehicle was modified by the technical services team at Modus to enable the successful burial of both the umbilical and pipelines in deep and shallow waters.

“To add to the challenge, the overall weight of the vehicle was reduced so that it could be accommodated by the available vessels. Mobilizing the single trenching system to perform these scopes had obvious benefits, particularly to a location with remote support facilities.”

The Vashishta field is located 30-35 km off the Amalapuram coast in the KG Basin, off the East Coast of India, at water depths of 250 to 700 meters.

ONGC started commercial production from the field through its Onshore Gas Terminal Plant in April.

Later that month, McDermott and its consortium partner LTHE completed engineering, supply, and installation of a series of pipeline end terminations (PLETs) and in-line tee structures (ILTs), a pipeline end manifold structure (PLEM), rigid jumpers and approximately 50 kilometers (30 miles) of umbilicals on the Vashishta and S1 fields.

Share this article

Follow Offshore Energy Today

Events>

<< Jul 2019 >>
MTWTFSS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31 1 2 3 4

Africa Oil Week 2020

For over 25 years Africa Oil Week has been the meeting place for Africa’s most senior E&P stakeholders.

read more >

CERAWeek 2020

 Each year, CERA clients gathered for a few days in Houston…

read more >

Offshore Technology Conference (OTC) 2020

The Offshore Technology Conference (OTC) showcases leading-edge technology for offshore drilling, exploration…

read more >

2020 EXPLORATION AND PRODUCTION STANDARDS CONFERENCE ON OILFIELD EQUIPMENT AND MATERIALS

The development of consensus standards is one of API’s oldest and most successful programs.

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply