Norway: First steel cut for Johan Sverdrup drilling platform

Norway First steel cut for Johan Sverdrup drilling platformFirst steel for the Johan Sverdrup drilling platform was cut Monday, February 15 at Aibel’s yard in Haugesund, Norway. The platform is a part of the Statoil-operated giant Johan Sverdrup development project in the Norwegian section of the North Sea.

 

“Aibel won the contract for the construction of the drilling platform about one year ago. Following an extensive planning and engineering process it feels good to start the construction of the first of four topside structures for the Johan Sverdrup project,” says Kjetel Digre, Statoil’s senior vice president for the Johan Sverdrup project.

“More than 14 000 people are involved in the Johan Sverdrup project on a daily basis in 2016, 1000 of them working for Aibel in Norway. We now see the effect of Norwegian industry being competitive, winning most of the principal contracts and equipment deliveries for Johan Sverdrup. We are dependent on all of these people to successfully deliver the project on time, to the required quality, and above all, without any HSE incidents,” Digre added.

The construction contract for the Johan Sverdrup drilling platform was awarded to Aibel in February 2015. The topside engineering work is being performed in Aibel’s Asker office, where also Statoil’s project team is located.

The 22 500-tonne topsides will consist of three modules, one of which will be built at the yard in Haugesund, one at the Deeline yard in Thailand, and one at Nymo’s yard in Grimstad. The modules will be assembled at Aibel’s yard in Haugesund in the autumn of 2017, before the platform is installed on the field in 2018.

In the summer of 2015 the pre-drilling templates were installed on the field. The Deepsea Atlantic semi-submersible will start pre-drilling wells on the field in March 2016.

“The most complex platform on the Johan Sverdrup field the drilling platform will come on stream at the end of 2018. We will then start phasing in the pre-drilled wells before production from the field commences at the end of 2019,” Digre says.

The cost development for the Johan Sverdrup project has been positive. So far the investment estimate for the first phase of the development has been reduced by 12 %.

“We are on track in the project, and have seen a positive cost development. This is still in an early stage of the project implementation: What matters now is to maintain focus throughout the process,” Digre said.

Share this article

Follow Offshore Energy Today

Events>

<< Dec 2019 >>
MTWTFSS
25 26 27 28 29 30 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

Africa Oil Week 2020

For over 25 years Africa Oil Week has been the meeting place for Africa’s most senior E&P stakeholders.

read more >

CERAWeek 2020

 Each year, CERA clients gathered for a few days in Houston…

read more >

Offshore Technology Conference (OTC) 2020

The Offshore Technology Conference (OTC) showcases leading-edge technology for offshore drilling, exploration…

read more >

2020 EXPLORATION AND PRODUCTION STANDARDS CONFERENCE ON OILFIELD EQUIPMENT AND MATERIALS

The development of consensus standards is one of API’s oldest and most successful programs.

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply