Offshore safety body finds electrical issues during Edvard Grieg audit

Norway’s safety watchdog, the Petroleum Safety Authority (PSA), has found five non-conformities and six improvement points during an audit of electrical facilities on the Edvard Grieg field, off Norway.

The PSA said on Monday that the audit, conducted from May 23 to June 1, targeted Lundin’s work to ensure compliance with the regulatory requirements for electrical facilities.

The audit was conducted in the form of meetings, discussions, document reviews, verifications, and functional testing of facilities on the Edvard Grieg platform.

The non-conformities identified during the audit were in regards to electrical facilities and ignition source control and technical conditions, work in and operation of electrical facilities, rooms for high-voltage installations, emergency power systems, and notification of hazard and accident situations.

Also, the offshore safety body found improvement points relating to installations in electrical facilities, barrier management, an overview of overrides and disconnections of safety systems and jumper logs, non-conformity handling, routines and control system for electrical systems, and temporary equipment.

The agency added that the audit placed particular emphasis on how Lundin is working to ensure that electrical facilities and those parts of the company’s management system covering the roles, responsibilities, and duties of the responsible person for electrical facilities during design, operation, modification, and maintenance, comply at all times with the requirements of the petroleum regulations.

The field is located in the central sector of the North Sea, 35 kilometers south of Grane and Balder, and has been developed using a fixed platform with a steel jacket and a full processing installation. There is also a separate jack-up rig for drilling and completing wells. Production from the field began back in 2015.

Lundin Norway is the operator with an ownership interest of 65 percent. Other licensees are OMV with 20 percent, and Wintershall Norge with 15 percent.

The operator was asked by the PSA to address non-conformities and provide an assessment of the improvement points by August 16, at the latest.

To remind, the PSA also found irregularities during an audit of working environment risk management and arrangements for employee participation on the Edvard Grieg field back in late June.

Share this article

Follow Offshore Energy Today

Events>

<< Nov 2018 >>
MTWTFSS
29 30 31 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 1 2

OSEA2018 International Conference

The OSEA International Conference is regarded as one of the preferred knowledge exchange platforms in the region and with over 18,000…

read more >

IMCA Annual Seminar

The focus of this year’s seminar is on the industry finding new strategies and ways of working in today’s…

read more >

Mauritanides 2018

Mauritanides (11-13 Dec 2018) is the foremost and largest event for companies seeking to invest in the Mining…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply