Otto Energy: Production Starts from Galoc Phase II (Philippines)

Otto Energy Limited  , on behalf of the Philippines Department of Energy (DOE) and the Galoc oil field Joint Venture, has today announced that production has started from the Galoc-5H and 6H wells drilled and completed under the Phase II development of the field.

Commissioning of the Galoc Phase II project represents a major achievement for the DOE, Otto Energy (the Operator) and the other partners within the Galoc Joint Venture. Initial production is 14,500 barrels of oil per day and the four well system is expected to be operated at 12,000 barrels of oil per day going forward.
Galoc has produced more than 11 million barrels of oil since it was commissioned in 2008. Ultimate recovery from the field, with the addition of Galoc-5H and 6H, is expected to be approximately 25 million barrels of oil
with end-of-field life extended beyond 2020.

Otto, as operator, has delivered Phase II from sanction to start of production in just over 14 months. Otto said that Phase II has been delivered safely and close to both the original budget and schedule set in August 2012. The project has experienced many challenges including maintaining safe operations during the recent Super Typhoon Haiyan and successful drilling of the horizontal wells through the Galoc reservoir.
Otto Chief Executive Officer Gregor McNab said: “Development of any offshore field presents unique challenges – particularly so for a field like Galoc in a remote location – and so I would like to thank the Otto team who have committed their significant experience and professionalism to successfully bring Galoc Phase II into production. This achievement is a credit to the Department of Energy which has worked relentlessly to promote oil and gas activity in the Philippines, our joint venture partners and all of our contractors.” 

McNab added:  “For Otto shareholders this represents a significant milestone, with our share of cash flow from Galoc set to  increase substantially, providing the company with additional funds to finance our exploration and development activities in South East Asia and East Africa. It also represents a major validation of our  capability as an operator as we consider new ways in which to grow the company and deliver returns to  shareholders.”

Press Release, December 05, 2013

 

Share this article

Follow Offshore Energy Today

Events>

<< Jan 2018 >>
MTWTFSS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31 1 2 3 4

FPSO Roundtables 2018

The entire FPSO value chain is now critically aware of how conventional modes of cooperation and project delivery must change in light…

read more >

International Petroleum (IP) Week 2018

International Petroleum (IP) Week, hosted by the Energy Institute (EI) is a renowned and highly respected event where leaders from the global…

read more >

8th Myanmar Oil, Gas & Power Summit

The Myanmar Oil and Gas Summit is the longest established Oil & Gas event in Myanmar. Every year the event is attended by government…

read more >

FPSO Europe Congress 2018

The FPSO Europe Congress 2018 builds on these themes, lending a particular focus to FPSO Value Preservation and Operational Excellence…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply