Prosafe-Westcon dispute over cost overruns lingers on

Prosafe, an operator of semi-sub accommodation rigs known as flotels, is still in dispute with Westcon over cost overruns related to Safe Scandinavia’s conversion from flotel to tender support vessel (TSV).

In its 2016 annual report on Thursday, Prosafe said that the litigation process relating to the final costs of the conversion of the Safe Scandinavia “remains ongoing” between Westcon Yards and Prosafe.

Westcon Yards and Prosafe Rigs entered into an EPC contract for the conversion of Safe Scandinavia into a tender support vessel on February 25, 2015.

The rig arrived at the yard in March 2015 and the plan was for the work to be completed in the first half of 2015. However, the project experienced delays thereby also delaying the contract start with the Norwegian oil company Statoil.

According to Prosafe, the conversion of the vessel has experienced a substantial cost overrun compared to the price estimate given by Westcon when the contract was entered into.

Following delays, the unit finally completed its acceptance testing and mobilized to the Oseberg Øst installation in the North Sea to start drilling support operations for Statoil in March 2016.

In mid-2016, Westcon made a claim through initiating litigation proceedings of NOK 306 million ($35.6M), plus interest. Prosafe Rigs disputed Westcon’s claim for additional compensation and presented a claim for repayment for NOK 270 million ($31.4M).

In case Prosafe does not get the claim, it will have to pay the NOK 306 million claim from Westcon and legal fees for both Westcon and Prosafe Rigs.

 

‘Potential court case’

 

The vessel’s owner further said on Thursday that a court mediation was held in mid-March 2017 without conclusive outcome. Mediation may continue between the parties, while a potential court case is scheduled for August and September 2017, Prosafe added.

As the final outcome cannot be reasonably measured, no asset or liability has been recognized relating to the settlement with the yard.

 

TSV contract 

 

Safe Scandinavia’s TSV contract with Statoil, which started in March 2016, has a firm period through to July 2018.

The Safe Scandinavia was built in 1984, upgraded in 2003, completed a life extension refurbishment in 2014, and finally converted in 2016.

Prosafe also said in its 2016 annual report that the market is at, or is near the bottom of the down cycle and that it is anticipated there will be a gradual recovery in demand and utilization from 2018.

Offshore Energy Today Staff

Share this article

Follow Offshore Energy Today

Events>

<< Dec 2019 >>
MTWTFSS
25 26 27 28 29 30 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

Africa Oil Week 2020

For over 25 years Africa Oil Week has been the meeting place for Africa’s most senior E&P stakeholders.

read more >

CERAWeek 2020

 Each year, CERA clients gathered for a few days in Houston…

read more >

Offshore Technology Conference (OTC) 2020

The Offshore Technology Conference (OTC) showcases leading-edge technology for offshore drilling, exploration…

read more >

2020 EXPLORATION AND PRODUCTION STANDARDS CONFERENCE ON OILFIELD EQUIPMENT AND MATERIALS

The development of consensus standards is one of API’s oldest and most successful programs.

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply