UK approves decommissioning plan for subsea facilities on MacCulloch field

MacCulloch field location map

UK authorities have approved the decommissioning plan for the subsea infrastructure and associated infield pipelines on the Chrysaor-operated MacCulloch field, located in the UK North Sea.

The decommissioning plan draft for the MacCulloch field was submitted by former operator ConocoPhillips back in June 2019.

Under the approved decommissioning plan, the anchors will be decommissioned in situ while all other subsea installations will be removed to shore for either re-use or recycling.

Also, all pipelines will be recovered to shore for reuse or recycling.

The operatorship of the MacCulloch field was transferred to Chrysaor following the acquisition of ConocoPhillips’ two UK subsidiaries for $2.675 billion in late September 2019.

The MacCulloch field is in the UK Central North Sea (CNS) Block 15/24b, in a water depth of 149 meters. Developed in 1996/97, the field had an expected life of ten years. Production started via the FPSO North Sea Producer in August 1997. The vessel was owned by the North Sea Production Company (NSPC).

MacCulloch production was conducted via two drill centers, West (WDC) and East (EDC), located 1.6 km and 2.9 km to the West and South East of the vessel location, respectively.

Oil and gas were exported from the FPSO vessel to the Repsol Sinopec-operated Piper Bravo platform through its owned 10” oil pipeline and 6” gas pipeline.

Preparation for decommissioning of the MacCulloch field started on May 3, 2015. The first phase of decommissioning continued until August 2015 when the North Sea Producer, the FPSO vessel, was removed from the area. Thereafter, the vessel was taken to Teesside by the owners for reuse and recycling.

During this initial decommissioning phase, the pipelines were flushed and made hydrocarbon free, and the risers and mid-water arches were retrieved for recycling/disposal.

In 2017, all of the wells were suspended with two isolation barriers using a light well intervention vessel, the Helix Well Enhancer.

MacCulloch field subsea facilities

Offshore Energy Today Staff


Spotted a typo? Have something more to add to the story? Maybe a nice photo? Contact our editorial team via email.

Also, if you’re interested in showcasing your company, product or technology on Offshore Energy Today, please contact us via our advertising form where you can also see our media kit.

Share this article

Follow Offshore Energy Today

Events>

<< Jan 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31 1 2

Africa Oil Week 2020

For over 25 years Africa Oil Week has been the meeting place for Africa’s most senior E&P stakeholders.

read more >

CERAWeek 2020

 Each year, CERA clients gathered for a few days in Houston…

read more >

Offshore Technology Conference (OTC) 2020

The Offshore Technology Conference (OTC) showcases leading-edge technology for offshore drilling, exploration…

read more >

2020 EXPLORATION AND PRODUCTION STANDARDS CONFERENCE ON OILFIELD EQUIPMENT AND MATERIALS

The development of consensus standards is one of API’s oldest and most successful programs.

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of OffshoreEnergyToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply